Rose Hill to Sooner 345-kV Line

  • Date: June 2012
  • Location: , Wichita KS
  • Category: Transmission, distribution, excavation and substation
  • Project Owner: Westar Energy

This Capital Electric Line Builders project consisted of 50 miles of new 345-kV line and 38 miles of 138-kV underbuilt on the same structures. Steel H-frame and steel single-pole structures were used on the project. Wire sizes were bundled 1590 ACSR on the 345-kV section and single 1192 ACSR on the 138-kV section.
RHS