Bombard Renewable Energy was the prime contractor on this project, managing civil, structural and electrical engineers, an architect, and earthwork, fencing and foundation contractors.

This power plant is the first of its kind in the world, integrating an existing 65-megawatt geothermal facility and ​a solar PV plant through the same utility interconnection point. The geothermal plant operation was not interrupted during the construction of the solar PV plant.


  • Location: Fallon, Nevada
  • Owner: Enel Green Power North America